In order to guarantee fairer share, SEDA Malaysia has capped the RE Installation capacities, particularly for Solar PV, for different categories. Capping is putting a quota or a limit for 6 months time period for the next 3 years. This 6-month time frame is the period allotted should there be next available set of quotas. The following tables show RE Quota for Solar PV Installation:
Solar PV Installation
Available MW Capacity for FiT Application | 2013 | 2014 | ||
H1 | H2 | H1 | H2 | |
Housing Developer | 0.00 | 0.00 | 0.00 | 0.00 |
Individual | 2.86 | 1.99 | 0.00 | 0.00 |
Non-individual (<500kW) | 0.00 | 0.00 | 0.00 | 0.00 |
Non-individual (>500kW) | 0.00 | 0.00 | 0.00 | 0.00 |
Allocated MW Capacity | 2013 | 2014 | ||
H1 | H2 | H1 | H2 | |
Housing Developer | 0.00 | 0.00 | 0.00 | 0.00 |
Individual | 4.70 | 0.47 | 0.00 | 0.00 |
Non-individual (<500kW) | 1.98 | 1.30 | 0.72 | 0.00 |
Non-individual (>500kW) | 32.26 | 26.24 | 30.53 | 0.00 |