Malaysia Feed in Tariff Rates depends on various factors. Such factors are:
- The type of RE technology used (whether it’s a small hydro, biogas, biomass, or solar PV)
- Capacity of the RE technology used
- RE installation commencement date
- Whether the RE technology has met any criteria that entitles for an additional bonus FiT rate
Solar PV FiT Rates
RE Installation Capacity | FiT Rate (RM/kWh) | Effective Period | Yearly Degression Rate |
Up to 4kWp installed capacity | 1.23 | 21 years | 8% |
Above 4kWp up to 24kWp | 1.20 | 21 years | 8% |
Above 24kWp up to 72kWp | 1.18 | 21 years | 8% |
Above 72kWp up to 1MWp | 1.14 | 21 years | 8% |
Above 1MWp up to 10MWp | 0.95 | 21 years | 8% |
Above 10MWp up to 30MWp | 0.85 | 21 years | 8% |
Additional if installed in building structures | +0.26 | 21 years | 8% |
Additional for using building materials | +0.25 | 21 years | 8% |
Additional for using assembled Solar PV modules | +0.03 | 21 years | 8% |
Additional for using assembled Solar inverters | +0.01 | 21 years | 8% |